Friday, November 20, 2009 21:39:52 CST: Shift_Notes/Control_Room_Shifts: 6891: Julian Felix
Friday, November 20, 2009 20:27:50 CST: Shift_Notes/Control_Room_Shifts: 6890: Gabriel Perdue
FirmwareUpgrade
Paul and I upgraded the firmware on the CRIM's installed
underground to v9 (fixed timing jitter bug). In the install process we damaged an inductor mounted on the back of CRIM 240 in Crate 1, but Boris was able to repair the damage within a half hour.
Run 846 is the first good run with the fixed timing in the CRIM.
Friday, November 20, 2009 20:26:45 CST: Shift_Notes/Control_Room_Shifts: 6889: Julian Felix
Friday, November 20, 2009 19:25:24 CST: Shift_Notes/Control_Room_Shifts: 6888: Julian Felix
Friday, November 20, 2009 19:08:35 CST: Shift_Notes/Control_Room_Shifts: 6887: Julian Felix
(Note- the dropped chain in run 845 was Crate 0 -Croc 8 - channel2)
Friday, November 20, 2009 19:03:09 CST: Shift_Notes/Control_Room_Shifts: 6886: Julian Felix
Dropped chain is back up after Gabe and Julian reset it underground. Started run 846
Friday, November 20, 2009 18:14:23 CST: Shift_Notes/Control_Room_Shifts: 6885: Julian Felix
Beam is back. starting run 845 series
Friday, November 20, 2009 17:37:10 CST: Shift_Notes/Control_Room_Shifts: 6884: Julian Felix
We got this message
Paul and I have taken control...
Friday, November 20, 2009 15:44:52 CST: Shift_Notes/Control_Room_Shifts: 6883: Julian Felix
We will restart in one hour. After Paul and Gabe get back.
Friday, November 20, 2009 15:43:52 CST: Shift_Notes/Control_Room_Shifts: 6882: Julian Felix
Run844_1 was stopped. Gave and Paul went underground.
Friday, November 20, 2009 15:27:32 CST: Shift_Notes/Control_Room_Shifts: 6881: Julian Felix
ShiftForms/MINERvA_Start_Shift
| Date | 11/20/2009 |
| Time | 15:21:09 |
| Shifter | Julian Felix and Donna Naples |
| shifter | |
| Review recent CRL entries | x |
| Review wiki | x |
| Run Sequence | 0Ped_then_3MaxpE.xml |
| Run | 844 |
| Subrun | 1 |
| Understand activities in the MINOS Hall | x |
| Comments | No beam in sight- continue Vittorio's LI run (thresholds 238 ) = MaxPE run. |
Friday, November 20, 2009 15:20:54 CST: Shift_Notes/Control_Room_Shifts: 6880: Julian Felix
This is the start of shifts.
JF
Friday, November 20, 2009 10:34:44 CST: Shift_Notes/Control_Room_Shifts: 6879: Vittorio Paolone
Chain 1-2-3(2) fell out again. No beam or estimate
yet from MCR. Staring new run with beam settings
Friday, November 20, 2009 10:20:36 CST: Shift_Notes/Control_Room_Shifts: 6878: Vittorio Paolone
Friday, November 20, 2009 9:11:53 CST: Shift_Notes/Control_Room_Shifts: 6877: Vittorio Paolone